HLSL Working Group

Issue Tracking

We use github issues to track the scenarios, deliverables, tasks and bugs for the HLSL working group.

HLSL Support project

The HLSL Support github project brings together issues in the wg-hlsl and llvm-project repos. Sometimes issues are tracked from external repos if they contribute to the overall goals of the HLSL working group.

Github projects add custom fields to issues / pull requests that are contained. The main fields HLSL Support adds are:

State

  • Not set - newly created issues are in this state and are not being actively managed.
  • Planning - scoping, creating sub-issues. Some amount of review required before this can move to the next state.
  • Ready - planning is complete, but it isn’t being worked on.
  • Active - it is being worked on.
  • Closed - issue is closed

Epic

An “Epic” is our name for some large piece of functionality we’re working towards. All work items associated with an Epic have this field set. We’re still figuring out what is an appropriate scope for an epic. Adding a new epic is something that should be discussed in the working group meeting.

Kind

Issues can be:

  • Scenario
  • Deliverable
  • Task
  • Bug

Note that we don’t use github’s new “Type” field because that isn’t necessarily consistent across repos.

More details on what the different kinds of issues are can be found below.

Iteration

The iteration field specifies when we expect an issue to be closed.

Estimate

This is a rough estimate of how long an issue will take to complete. Values include:

  • Hours, Days, Week, Sprint, Multiple Sprints
  • Break Up - this estimate is set to indicate that we think this issues need to be broken up into smaller chunks
  • Umbrella - this indicates that this issue is actually an “umbrella” one that exists to hold multiple sub-issues that are estimated separately.
  • n/a - it doesn’t always make sense to provide an estimate for an issue, in which case we can set it to n/a.

Blocked

Issues can be blocked for some different reasons:

  • PR - waiting for a PR to complete
  • Refinement - waiting for agreement that it is ready to go from Planning to Ready
  • Blocked - waiting for some other dependency before work on this one can continue
  • Review - waiting on design review

When marking an issue as “Blocked” we try and add a comment on the issue explaining why.

Priority

We use the priority field to determine what’s most important to work on next.

Kinds of Issue

Scenario

A scenario describes a set of things we want to accomplish as part of delivering an Epic. Example scenarios: “Implicit Resource Binding”, “Offload Testing Framework”.

Generally, we timebox Planning for a scenario, usually around 1 week, but some scenarios may require more planning than others. We track the planning work with deliverable and task sub-issues. The main goal of planning is to determine the scope of the scenario and the deliverables that make it up. Once the planning deliverable is complete, and has been reviewed, the scenario can move to the Ready state.

The scenario becomes Active once any of its sub-issues become active. The scenario is Closed once all of its sub-issues are closed.

Deliverable

Deliverables are sub-issues of Scenarios. These are major chunks of work that we expect to complete, usually sequentially, for the scenario. Example deliverables: “Build functional tests”, “Design”, “Implement”.

As with scenarios, we timebox Planning for a deliverable and work on scoping the deliverable and identifying tasks during this time. Before the deliverable can move to the Ready state it needs to be reviewed and all of the task sub-issues are also Ready. This means that all of the sub-issues have been estimated.

We move a deliverable to Active once we start working on one of the tasks. At this point we can set the deliverable’s iteration based on the estimates of those tasks.

Once all the tasks are closed, the deliverable can be closed.

Task

Tasks are the smallest unit of work we track (although we do allow for umbrella tasks with sub-issues if appropriate). We aim to have tasks that can be completed in a single iteration.

During task planning we work on the scope and plan for the task. If there’s significant design work then this is likely to have been tracked by another task. After the task has been reviewed and an estimate set it can move to Ready.

When a task goes from ready to active, we set the iteration to when we expect to complete it.

Bug

Bugs are things we didn’t plan to do, so we don’t spend a lot of time estimating them. If significant work is involved in fixing it then we’ll need to create other issues to track that as appropriate.

Implementation Tasks / Bug Tracking

Issues that track tasks or bug fixes that involve changing code in Clang/LLVM are tracked in the llvm-project repo.